Gather the public grid data
Utility hosting capacity maps, feeder and bank ratings, load forecasts and the generators already on the line, for the feeder that serves the site.
We model the feeder your battery would connect to, find what the utility will flag, and price the fix and the time it takes before you apply.
We study the one feeder that would serve the battery, at the hours that stress it most.
Utility hosting capacity maps, feeder and bank ratings, load forecasts and the generators already on the line, for the feeder that serves the site.
We rebuild the feeder in OpenDSS (Open Distribution System Simulator, the open engine from the Electric Power Research Institute): bank, wires, loads and generators.
Charging is tested against the highest night load. Discharging is tested against the lowest daytime load. Those two hours push the grid hardest.
Reverse power, ground overvoltage, islanding, voltage and thermal limits, and New York's Standardized Interconnection Requirements (SIR) screens.
We step the battery up until the first limit fails. The size just below is the largest fit, and the failing limit names the fix. Sample run: 0.70 MW, set by the bank while charging at night.
How to read it. Power comes in at the top and flows down through the substation bank to the feeders. Moving dots show the flow: blue is normal, magenta runs back toward the grid, and bigger, faster dots carry more power. Circles are protective relays, numbered by the IEEE C37.2 standard (Institute of Electrical and Electronics Engineers). Dashed cyan parts are proposed.
Scroll the cards. Each one lights up its device on the drawing.
When the battery sends out more than the feeders use, power flows backward through the substation bank toward the higher-voltage line. In the sample run, 1,919 kW flows back.
Many substation banks are wired delta on the high side, so a ground fault on that line is hard to see from below. A battery that keeps feeding it can push the healthy wires far above normal voltage.
If the utility opens the feeder, the battery must stop and not keep a piece of the grid alive by itself. Where generation is high against minimum load, the utility can add direct transfer trip (DTT), a signal that trips the battery.
Pushing power out raises voltage where the battery connects. A project fails the screen if it pushes voltage outside ANSI C84.1 Range A. In the sample run the connection point rose from 1.008 to 1.031 per unit.
Charging at night adds to the night load on the bank and the wires. In the sample run, charging 2.50 MW at the highest night hour would load the bank to 148% of its rating.
A weak point on the grid swings more when a battery ramps. The screens want short-circuit capacity more than 25 times the battery rating, and flicker (Pst) of 0.35 or less. The sample site scored 9.9.
Green on the drawing marks where each fix goes.
Three voltage transformers on the bank's high side feed a 59N relay. On a ground fault it trips the feeder breakers, which takes the battery off.
A reverse-power relay, or a battery controller that caps export, keeps flow at the bank going forward. The SIR requires function 32 when a battery's net export is limited.
A utility recloser at the point of common coupling (PCC) carries reclosing, sync check, voltage, frequency and reverse-power relays, so the utility can isolate the site. The exact device is set in the utility's study (UNCONFIRMED until then).
The SIR requires inverters listed to UL 1741 SB. Their settings can absorb reactive power to hold voltage down (power factor, volt-var, volt-watt). It is often the cheapest fix.
A smaller battery, or a point of interconnection (POI) on a higher-voltage line, can clear several limits at once. Grid Studio shows that the voltage of the line you connect to decides how big a battery fits.
Charge only when the bank has room, or cap the charge rate. In the sample run the night charge limit was 0.70 MW, while daytime discharge could reach 3.30 MW.
Public New York figures for the most common substation fix, 3V0 protection on one bank, and for the study that prices it.
The utility's clocks in the SIR, in Business Days (BD). About 21.5 Business Days make a month.
Above $10,000 of upgrades: 25 percent within 90 Business Days, then 75 percent within 120.
When the utility starts building is UNCONFIRMED; ask for the date in writing.
We start with the feeder model and finish with the fix, the cost and the timeline.